House update [Feb. 1st, 2004|02:18 pm]
Callicrates
[Current Mood |sleepysleepy]

When we went to visit on Friday morning they were busy framing the first floor. By Saturday it appeared complete. My guess is that they'll be getting another shipment of lumber on Monday (I hope) and will start work on the second floor on Monday or Tuesday.

Barring any huge delay in the rest of the neighborhood, it looks like our house will be the very last one finished. We would have been keeping pace with two others on our street except for a two-week delay getting the pipes for the radiant heat laid down. I hope that delay doesn't recur on the second floor...

If I had to guess, I'd say that our mid-April close date is pretty unrealistic and that the first of May is a more likely bet.